Nip Impressions logo
Sun, Apr 28, 2024 17:27
Visitor
Home
Click here for Pulp & Paper Radio International
Subscription Central
Must reads for pulp and paper industry professionals
Search
My Profile
Login
Logout
Management Side
Pulp mill project on schedule, facility scheduled to begin production in second quarter

SANTIAGO, Chile -- Empresas CMPC announced Friday 20 January 2015 that its Guaiba 2 Project, in the State of Rio Grande do Sul, Brazil, remains on budget and on schedule for start-up in the second quarter of 2015.

CMPC said the facility was at 88% physical completion as of 31 December 2014. The main milestones achieved in the project's execution to date include the completion of the electric substation, the startup of the water supply system, the hydrostatic testing of the digester and, most recently, the first ignition of the recovery boiler, the company said.

Approved by the Board of Empresas CMPC in December 2012, the $2.1 billion expansion of the Guaiba pulp mill will add 1.3 million tons of eucalyptus pulp capacity, bringing CMPC's total hardwood and softwood pulp capacity to 4.1 million tons per year. The mill is 100% wood self-sufficient, and will lower CMPC's average pulp cash cost. During the construction phase, the expansion employed more than 9,000 highly qualified workers, one third of who were from local communities.

CMPC said the next steps at the project will include the pre-operational chemical cleaning of the recovery boiler, the steam blow of the pipe lines to the turbogenerators, migration of the control systems to the new control room, putting in operation a chipping line in the woodyard and continuing of the commissioning activities in other systems.


Printer-friendly format

 





Powered by Bondware
News Publishing Software

The browser you are using is outdated!

You may not be getting all you can out of your browsing experience
and may be open to security risks!

Consider upgrading to the latest version of your browser or choose on below: